Project Purpose Management assignment plan for Globex

Question

Task: How can Globex utilize Project Purpose Management assignment to develop an effective project management plan that ensures the business growth and expansion in future

Answer

1. Introduction<
1.1. Management plan of the Project Purpose

The Project Purpose Management assignment has been designed to address the networking issues in the infrastructure of the Globex. The issues are resulting in creating unwanted bugs in the System. Thus, the new Project Purpose Management assignment must be planned to upgrade the System. System up gradation can be done by adopting new networks hardware in the System. The software tools must also be installed in the Systemas per the hardware requirements. The Management plan of the Projectwill help to execute the Project within the specified time and cost. An effective Management plan of the Project helps in meeting the Stakeholdersexpectations.

2. A summary on Project Charter 2.1. Constraints/Assumptions
2.1.1. Constraints Chart

Team Member

Role

Constraints Factor

Chameera

Project Manager

1.      Leading this Project Purpose Management assignment is not an easy task and a person needs proper leadership skills to lead the Project. It is the main factor of the constraint in the Project Charter.

2.      The Project Purpose Management assignment. must not give excess work pressure to the team. They must give positive notes to the team for motivating them. Motivation can be a significant constraint factor if not given properly.

Kogulnath

Network Engineer

1.      Acquire of information is not a short time task. The responsible person has to take help from several sources, and it has also been seen that the information can be false.

2.      The installation process is the primary constraint in every Project. The single person cannot do it in the group. Installation and execution need teamwork to execute the Project on time.

Kavinga

Test Engineer

1.      Constraints can be found while purchasing the required resources from the suppliers. Suppliers can raise several issues regarding the price of the resources.

 

2.1.2. Assumptions

Team Member

Role

Assumption Factor

Chameera

Project Manager

1.      The main task of this The Project Purpose Management assignment is to prepare a proper work break down structure according to the timeline of the Project. It can be done efficiently by the Project Manager.

2.      When a quality plan of the management is used for monitoring the Project, it means the monitoring can be done effectively.

Kogulnath

Network Engineer

1.      The quality plan of the management will help to check the standard of the mesh network. Thus, it can be designed and implemented successfully in the System.

Kavinga

Test Engineer

1.      When a management plan of the Project holds a proper communication plan, then the training event becomes more manageable for the test engineer.

2.      The network can be adequately tested if the Project has been executed on time. It will help in cross-checking the Project several times.

 

3. Scope Management
3.1. Work Breakdown Structure of the Project with budget

WBS

Task Name

Duration

Start

Finish

Resource Names

Cost

1

Start of the Project

65 days

Wed 18-03-20

Tue 16-06-20

 

$122,800.00

1.1

   Make the Management plan of the Project

4 days

Wed 18-03-20

Mon 23-03-20

 

$960.00

1.1.1

      Make the Project Charter

1 day

Wed 18-03-20

Wed 18-03-20

Project manager

$240.00

1.1.2

      verify the Management plan of the Project with the stakeholders

1 day

Thu 19-03-20

Thu 19-03-20

Project manager

$240.00

1.1.3

      Verify the Project Charter Plan with the Stakeholders

1 day

Fri 20-03-20

Fri 20-03-20

Project manager

$240.00

1.1.4

      Acquire of data

1 day

Mon 23-03-20

Mon 23-03-20

Project manager

$240.00

1.2

   Gather of data from different sources

10 days

Tue 24-03-20

Mon 06-04-20

 

$1,680.00

1.2.1

      Define the Functionalities

1 wk

Tue 24-03-20

Mon 30-03-20

Network engineer

$800.00

1.2.2

      Verfying the list of resources according to the requirements

4 days

Tue 31-03-20

Fri 03-04-20

Test Engineer

$640.00

1.2.3

      Initiation of the Project

1 day

Mon 06-04-20

Mon 06-04-20

Project manager

$240.00

1.3

   Make the scope Management Plan of the Project

6 days

Tue 07-04-20

Tue 14-04-20

 

$1,440.00

1.3.1

      Schedule the budget

1 day

Tue 07-04-20

Tue 07-04-20

Project manager

$240.00

1.3.2

      Allocate the task to the project team

1 day

Wed 08-04-20

Wed 08-04-20

Project manager

$240.00

1.3.3

      assessing the possible Risk

1 day

Thu 09-04-20

Thu 09-04-20

Project manager

$240.00

1.3.4

      Make the Quality plan of the management

1 day

Fri 10-04-20

Fri 10-04-20

Project manager

$240.00

1.3.5

      Cross check the Management plan of the Project with the Quality plan of the management

1 day

Mon 13-04-20

Mon 13-04-20

Project manager

$240.00

1.3.6

      Design and Plan the Project

1 day

Tue 14-04-20

Tue 14-04-20

Project manager

$240.00

1.4

   make the concept of the design

3 days

Wed 15-04-20

Fri 17-04-20

 

$480.00

1.4.1

      Execute the concept of the design

1 day

Wed 15-04-20

Wed 15-04-20

Network engineer

$160.00

1.4.2

      Verfy the design with the Stakeholders

1 day

Thu 16-04-20

Thu 16-04-20

Network engineer

$160.00

1.4.3

      Building the logical Network Design

1 day

Fri 17-04-20

Fri 17-04-20

Network engineer

$160.00

1.5

   Make the architecture of the design

11 days

Mon 20-04-20

Mon 04-05-20

 

$1,760.00

1.5.1

      Study the detailing of the design

2 days

Mon 20-04-20

Tue 21-04-20

Network engineer

$320.00

1.5.2

      Verify the detailing of the design

1 day

Wed 22-04-20

Wed 22-04-20

Network engineer

$160.00

1.5.3

      Approve the design specification with the stakeholder

1 day

Thu 23-04-20

Thu 23-04-20

Network engineer

$160.00

1.5.4

      Seek stakeholder comments regarding the design

1 day

Fri 24-04-20

Fri 24-04-20

Network engineer

$160.00

1.5.5

      Build the Configuration

6 days

Mon 27-04-20

Mon 04-05-20

Network engineer

$960.00

1.6

   Purchase of the hardware devices according to the resource list

10 days

Tue 05-05-20

Mon 18-05-20

Albury[1],

Griffith[1],

Orange[1],

Wagga Wagga[1]

$111,760.00

1.6.1

      verify the hardware devices according to the resource list

2 days

Tue 05-05-20

Wed 06-05-20

Project manager

$480.00

1.6.2

      Build the network design

2 days

Thu 07-05-20

Fri 08-05-20

Network engineer

$320.00

1.6.3

      implement the network design

2 days

Mon 11-05-20

Tue 12-05-20

Network engineer

$320.00

1.6.4

      Configure it according to the requirements

2 days

Wed 13-05-20

Thu 14-05-20

Network engineer

$320.00

1.6.5

      Test the quality of the Processes

2 days

Fri 15-05-20

Mon 18-05-20

Network engineer

$320.00

1.7

   test each of the processes according to the standards

4 days

Tue 19-05-20

Fri 22-05-20

 

$640.00

1.7.1

      Verify the tests

1 day

Tue 19-05-20

Tue 19-05-20

Test Engineer

$160.00

1.7.2

      Gather the results of the tests

1 day

Wed 20-05-20

Wed 20-05-20

Test Engineer

$160.00

1.7.3

      Configure after testing

1 day

Thu 21-05-20

Thu 21-05-20

Test Engineer

$160.00

1.7.4

      Verify the standards according to the clients requirements

1 day

Fri 22-05-20

Fri 22-05-20

Test Engineer

$160.00

1.8

   make quality checks according to the quality plan of the management

5 days

Mon 25-05-20

Fri 29-05-20

 

$1,200.00

1.8.1

      Verify with the stakeholders

1 day

Mon 25-05-20

Mon 25-05-20

Project manager

$240.00

1.8.2

      Approve the results

1 day

Tue 26-05-20

Tue 26-05-20

Project manager

$240.00

1.8.3

      Seek stakeholders comments while approving

1 day

Wed 27-05-20

Wed 27-05-20

Project manager

$240.00

1.8.4

      Organize minutes meetings to discuss the results

1 day

Thu 28-05-20

Thu 28-05-20

Project manager

$240.00

1.8.5

      Gather materials for training

1 day

Fri 29-05-20

Fri 29-05-20

Project manager

$240.00

1.9

   Gather information for training sessions

5 days

Mon 01-06-20

Fri 05-06-20

 

$1,200.00

1.9.1

      verify the information

1 day

Mon 01-06-20

Mon 01-06-20

Project manager

$240.00

1.9.2

      Schedule the training sessions according to the materials

1 day

Tue 02-06-20

Tue 02-06-20

Project manager

$240.00

1.9.3

Project Purpose Management assignmentstakeholders schedules

1 day

Wed 03-06-20

Wed 03-06-20

Project manager

$240.00

1.9.4

      execute the training processes

1 day

Thu 04-06-20

Thu 04-06-20

Project manager

$240.00

1.9.5

      Deploy the Project

1 day

Fri 05-06-20

Fri 05-06-20

Project manager

$240.00

1.10

   assembles the test results

3 days

Mon 08-06-20

Wed 10-06-20

 

$720.00

1.10.1

      verify the Product

1 day

Mon 08-06-20

Mon 08-06-20

Project manager

$240.00

1.10.2

      Cross check the Product

1 day

Tue 09-06-20

Tue 09-06-20

Project manager

$240.00

1.10.3

      Completion of the Project

1 day

Wed 10-06-20

Wed 10-06-20

Project manager

$240.00

1.11

   Handover the project

4 days

Thu 11-06-20

Tue 16-06-20

 

$960.00

1.11.1

      signoff the Project

1 day

Thu 11-06-20

Thu 11-06-20

Project manager

$240.00

1.11.2

      Make the documents archived for future purpose

1 day

Fri 12-06-20

Fri 12-06-20

Project manager

$240.00

1.11.3

      Give feedback according to the Result

1 day

Mon 15-06-20

Mon 15-06-20

Project manager

$240.00

1.11.4

      recognise the Performance of the Project

1 day

Tue 16-06-20

Tue 16-06-20

Project manager

$240.00

 

3.2. Change Control Management
Types of change Description

Corrective Actions Corrective actions must be implemented in those critical activities that are needed to be changed. These actions will help in the improvement of the Project. The correction must be made when it is needed. Additional corrections lead to delay in project execution (Demirkesen & Ozorhon, 2017). The delay in Project leads to high cost and time for executing. It may fail the Project.

Preventive Actions Preventive actions aretaken when the risk canbe detected before it happens. It helps the team to take preventive measures for the risk so that the Project must not get affected by the risk (Demirkesen & Ozorhon, 2017). Risk register tool is used to detect the Project and take preventive actions according to that. Defect Repairs On this Project Purpose Management assignment it is identified that the Project also needs repairmen for mitigating the risks. Some risks cannot be detected previously, and thus they occur suddenly. That time the Project needs to be repaired by employing mitigating actions (Demirkesen & Ozorhon, 2017). It will help in making the Project bug free so that it can deliver service for a long time.

4. Time Management
4.1. A short brief on Project Time Management

One of the most important factors behind any project is "time-management." This is the best possible way to complete the project correctly and doing the "right thing at the right time." It includes various factors like:
a. "Effective planning"-Listing the essential tasks and targeting to complete it within the given time could be defined as "effective planning" Also, listing and completing the tasks which have high priority in the project must come on the top of the list.
b. "Deadline setup"- Setting up the deadline for the task and trying to complete it as soon as possible before the deadline.
c."Schedule"-Scheduling the time for each task required to be completed at the right time plays a significant role in the "time-management" factors.
d."Prioritizing tasks"- Some tasks are urgent and need to be completed before doing the other tasks. Giving priority to the right task is also very important to manage time.
e. "Proper planning"- It plays a vital role related to "time-management." For an individual or group in the organization, proper planning motivates to achieve the goal and makes a "sense of direction."

Besides the factors identified on this Project Purpose Management assignment, some other outcomes may occur, which can hamper the "time-management." This may result from delays in project success. Setting up a reward system for the employees working in the project will motivate them to work faster. Also, setting up "team-goal" instead of individual goals is an excellent approach for the "time-management" system (FRANCIS & OLORI, 2017). Climate problems, transportation delay, fund shortage, lack of labors and employees, high cost of engineers and skilled technicians, an insufficient supply of raw materials and, fluctuation in the cost of materials and equipment, which are essential for the project completion. These outcomes could be resolved to some extent by the "effective planning method." Proper contracts with documents with the suppliers and other employees reduce the risk, and time could be saved. Handling climate factors is not in the hand of the project authority, but precautions should be taken in this case to handle these issues. These are the various factors by which the "time-management" of a project could be handled successfully so that the productivity and pace in the project construction lead to the ultimate success.

5. Project Purpose Management assignment Cost Management and Budget Plan
5.1. Wagga Wagga

Types of change

Description

Corrective Actions

Corrective actions must be implemented in those critical activities that are needed to be changed. These actions will help in the improvement of the Project. The correction must be made when it is needed. Additional corrections lead to delay in project execution (Demirkesen & Ozorhon, 2017). The delay in Project leads to high cost and time for executing. It may fail the Project.

Preventive Actions

Preventive actions aretaken when the risk canbe detected before it happens. It helps the team to take preventive measures for the risk so that the Project must not get affected by the risk (Demirkesen & Ozorhon, 2017). Risk register tool is used to detect the Project and take preventive actions according to that.

Defect Repairs

On this Project Purpose Management assignment it is identified that the Project also needs repairmen for mitigating the risks. Some risks cannot be detected previously, and thus they occur suddenly. That time the Project needs to be repaired by employing mitigating actions (Demirkesen & Ozorhon, 2017). It will help in making the Project bug free so that it can deliver service for a long time.

 

5.2. Griffith

Network Requirement

Hardware Requirement

Cost in AUD (Australian Dollar)

LAN (Local Area Network)

Core i3/i5/i7 processor, 8GB RAM with HYPER-V technology/Esxi dedicated machine/ Core i3 processor, 2x4 GB RAM (2 dedicated machines)

 

 

 

30,000 AUD

WAN (Wide Area Network)

VPN (Site to site)

WAN failure

Guest VLAN (Virtual LAN)

Core i7 processor, 16 GB RAM, nondedicated machine

25,000 AUD

QoS

Windows 10 Professional, Windows Server 2012 R2

2,500 AUD

 

5.3. Albury

Network Requirement

Hardware Requirement

Cost in AUD (Australian Dollar)

LAN

Core i3/i5/i7 processor, 8GB RAM, HYPER-V/Esxi dedicated machine/core i3, 2x4 GB RAM, 2 dedicated machines/core i7, 16 GB RAM, non-dedicated machine

25,000 AUD

WAN

Site to Site VPN

 

5.4. Orange

Network Requirement

Project Purpose Management assignment Hardware Requirement

Cost in AUD (Australian Dollar)

LAN (Local Area Network)

Core i3/i5/i7 processor, 8GB RAM with HYPER-V technology/Esxi dedicated machine/ Core i3 processor, 2x4 GB RAM (2 dedicated machines)

 

25,000 AUD

WAN (Wide Area Network)

Site to Site VPN

 

6. Quality Management
6.1. Quality Checklist

Quality Requirements

YES/NO

Reasons

Does the Project have an effective quality plan of the management

Yes

The Project has an effective quality plan of the management as it will help to check the quality of task in the Project Purpose Management assignment. Since it is a network-based Project; quality plays a central part in the Process. Thus, aquality plan of the management helps to maintain the standards of the Project. The quality of the resources must be checked so that they can be applied in the Project.

Do all the stakeholders haveaccepted the quality plan of the management

Yes

The quality plan of the management serves a complete solution for checking the standards of the Project. Thus, the quality plan of the management has been approved by all the stakeholders.The stakeholders thoroughly check the plan and then approve it for the Project. It will help the stakeholders to check the standards and ensure that the Project has been executed without any bugs.

Do all the stakeholders have equal access to the quality plan of the management

No

The stakeholders are grouped according to their positions in the Organization. Thus, they got the right to access the quality plan of the management according to their position. Like, the Project Director and the Project Manager have access to use all features in the plan. However, the Project Purpose Management assignment team has restricted access to the plan.

Does the plan is adequate for meeting the standards

Yes

The plan has been designed in such a way so that it can meet the standards of the Project. It will help in executing the Project efficiently. The plan can meet the stakeholder’s requirements. The monitoring of the Project can be done effectively using this plan. The plan can be modified according to the change management of the Project. It will help to give an integrative look to the Project.

Does the quality plan of the management have the consistency to meet the whole project plan

Yes

The quality plan of the management has the capacity to meet the purpose of the Project. It can give assurance about meeting the standards in the Project. The Project standards are planned as per the project Plan. Then the quality plan of the managementhas been designed according to the standards. In reality, the quality plan of the management is interrelated to the Project Plan.

Does the quality metrics of the Product have been reviewed by the quality plan of the management

No

The Project is on its running stage. All the stages identified on this Project Purpose Management assignment have not been completed yet. Thus, all the quality of products has not been checked by the Project Team. The project team is working on its schedule and checking the metrics. The metrics are checked of those Products that have been finished by the team. The metrics check is done on several stages. The team members do the initial metric check, and the Project Manager does the final check. It helps to bring out the effectiveness of the Product.

Does the quality metrics of Process have been reviewed

Yes

The quality metrics have been reviewed by both the team and the project manager. The quality metrics show that the Process is going according to the schedule. Moreover, it can be executed within the specified cost. The quality plan of the management also focuses on the Project cost. It leads to failure of the Project due to the lack of cost. The Process has been reviewed frequently so that the time and cost of the Project can be maintained.

Does the quality of the Project is capable of mitigating the issues in the existing System

Yes

Project Purpose Management assignment standards have been set in such a way to address the issues. It will help in addressing the drawbacks of the existing System. Through the quality plan of the management, the Project can be executed successfully. Thus, the issues in the existing System can also be mitigated efficiently. The result will be productive for the Organization.

 

7. Human Resource Management
7.1. Issues on Human Resource

Issues

Impact on Organization

Impact Level

Lack of communication between the members

Lack of communication is one of the significant issues of Human resource management. As a result, it fells a significant impact on the Organization (Sparrow, Brewster, & Chung, 2016). The lack of communication between the team members makes delay in the Project. Sometimes Proper monitoring also fails to address the issues (DeCenzo, Robbins, & Verhulst, 2016). The issue must be detected at the initial stage and should be mitigated at once. Lack of communication occurs when the two or more members belong to the different cultures. It results in a big communication gap and can affect the Project.

High

Lack of proper monitoring in the Project

It is one of the probable issues that often observe in Project Management. Lack of monitoring leads to delay in the Project. Project members cannot execute the task effectively (Bratton & Gold, 2017). Due to lack of monitoring person, the team gets puzzled while executing the complex task. It results in a delay in the Project. In worst cases, the Project might get stop due to lack of proper execution time.

High

Creating discrimination between the Employees

The employees are discriminated according to Performance and culture. Some employees make a particular repo with the leaders that help to grow faster in the Organization. Sometimes unwise employees get promoted instead of wise employees (Armstrong & Taylor, 2020). It leads to frustration among the employees. It is also observed on this Project Purpose Management assignment, productivity decreases and as projectsgets delayed.

Medium

Allocation of the job uniformly

The officials in the Human resource must study their employees and allocate the task according to the excellency factor. It helps to execute the task within the specified time. It prevents creating extra pressure on the employees. Allocating the task uniformly leads to extra pressure on the Employees. The employees get depressed with the workload (DeCenzo, Robbins, & Verhulst, 2016). As a result, the productivity of the employee gets decreased. Moreover, the employees get frustrated on the Organization. It leads to employee turnover.

Low

Lack of training

Due to lack of training, the employees failed to acquire knowledge on the various tasks. As a result, the countof skilled laborsgets decreased in the Organization. The newcomers in the Organization must get proper training before joining in the main task (Bailey, Mankin, Kelliher, & Garavan, 2018). It will help in gaining the proper knowledge in respect of both practical and theoretical.

Low

 

7.2. Conflict Management

Conflicts

Responsible Person

Impact on Organization

Impact level

The Conflict between the stakeholder

Project Manager

When stakeholders get involved in the Conflict, it leads to a massacre situation in the Organization. The Organization cannot address these issues with leadership goals. It can be mitigated through instant minute’s meetings. The stakeholders must be involved equallyin the Process of the Project (DeCenzo, Robbins, & Verhulst, 2016). The feedback must be taken from each of the stakeholders for improving the Performance of the Project. The Project can be improved according to the feedback for the stakeholders.

High

The Conflict between the team members

Project team

Conflict occurs while working in the same Project Purpose Management assignment. However, those conflicts must be mitigated at once to resolve the situation (Sparrow, Brewster, & Chung, 2016). These conflicts lead to a delay in work progress. As a result, the Project process gets delayed, and the Project might get the stop. Proper monitoring can be made to resolve these conflicts. It must be done by the Project Manager while doing the monitoring of the Project (Bratton & Gold, 2017). The Project Manager should study each of the Performance of the team member so that no one involves them in the Conflict.

Medium

Conflict during delivery

Test Engineer

After the test done by the test engineer, it’s time for project delivery. Conflicts can occur during the project delivery because some of the stakeholders can request for delaying the delivery (Bailey, Mankin, Kelliher, & Garavan, 2018). They want to say that the Project must be cross-checked several times before doing the delivery.

Medium

 

Conflict on processing the Project

Project Manager

The processing of the Project has been done according to the plan done by the Project Manager (Armstrong & Taylor, 2020). The Project Manager must seek feedback from the stakeholders regarding the Process of the Project. The Conflict starts here in the Project. Each of the Stakeholders places their feedback that does not match with each other. It leads to Conflict in management.

Medium

 

 

8. Communication Managementfor Project Purpose Management assignment
8.1. Schedule of Meetings

Date

Description of Change

Reason

Author

Version Number

18/03/20

Initial draft

Not available

Project manager

Version 1

25/03/20

Planning of the Project

For increasing the Performance of the Project

Project manager

Version 2

8/04/20

Submitting the list of resources

Verification of the resource list with the stakeholders

Test Engineer

Version 3

15/04/20

Settlement of the final changes

The settlement will be done as per the expectations of the stakeholders

Network engineer

Version 4

16/06/20

Submission of the final draft

Not available

Project Manager

Version 5

 

8.2. Communication mode used in Meeting

Meeting number

Purpose of the Meeting

Communication mode

Meeting 1

Presentation of the initial draft and verifying it with the stakeholders. It will help in drawing the feedback from the stakeholders and help in making effective changes in the Project.

Minutes meeting and Email

Meeting 2

Discussion of the Project in detail so that the Performance of the Project can be increased. The Performance will be increased according to the Purpose of the Project Purpose Management assignment. The purpose of the Project must be met, and for that, effective changes must be done to increase the Performance. The project performance must not get hampered due to the lack of change management. The efficiency of the Project must not get hampered due to the lack of monitoring.

Email, Minutes Meeting

Meeting 3

The resource list of the Project must be verified according to the purpose of the Project. The network engineer must involve in gathering information from various sources. As a result, useful information can be acquired for the Project. The resource list must be verified and cross-checked with the purpose of the Project. The purpose of the Project must get meet so that no bugs can occur in the future.

Email, Minutes meeting

Meeting 4

The last changes must be settled so that the operations of the Project must be made smoothly. Further changes will make delay in the Project. The changes in the Project must be met and discussed with the stakeholders. It will help the stakeholders to know about each of the Process that is going on the Project. The Process must be executed according to the feedback from the Stakeholders.

Minutes meeting, video conferencing

Meeting 5

After the completion of the Project, the final submission must be made by doing the meetings with the stakeholders. The stakeholders must get satisfied with the Process of the Project. There should be no miscommunication between the stakeholders. The stakeholders must verify and check the results. It will help in mitigating the bugs in the future condition.

Minutes meeting, email and video conference

 

9. Risk Management
9.1. Risk Assessment

Risk

Description of the risk

Probability level

Impact level

Hacking and cyber threats

Hacking is a frequent but severe risk in the present day. Hackers can inject malware into the system leading to malfunctioning of the whole server or ultimate breakdown of the system (Baldwin, Chan, & De Morentin, 2019).

Medium

High

Financial problems

Shortage of cash, delay issues in the payment procedures.

Medium

High

Computer server, network, and computing-related problems

Computer servers may malfunction for different types of hardware and software issues, such as hard-disk or RAM failure, crashing of OS (Operating System) or other software installed in the machines, slow network or disconnection of the network due to router malfunction or crashing (Rezaei, Rostami, Ghafouri, Fashkhorani, & Ahmadi, 2016).

High

High

Malfunctioning of power systems or ultimate failure

Power malfunction could occur due to voltage fluctuation and short circuits. It may result in an ultimate power failure.

Medium

High

Absenteeism or resigning of employees

Illness is a severe and essential factor for this reason. Accidents may occur for which the employee is unable to join the work. Resigning of employees is also should be considered. It can happen due to getting better opportunities or for the delay in payments or low salary issues.

Medium

Medium

Error or bug in the whole system network

Improper installation of the operating systems and other software is the main reason for it. It may happen due to inexperienced engineers and novice technicians. Employing the proper person for this job is the measure of this problem.

Medium

High

Outcomes and miscellaneous factors

It can happen due to worse climate issues which can slow down the total project or delay in completing the project

Low

Medium

 

9.2. Project Purpose Management assignment Risk Rating

ID

Risk

Likelihood

Impact

Severity

Mitigation Strategy

R1

Hacking and cyber threats

Medium

High

High

Taking steps to secure the whole system by discussing with the higher authority and employing security expert engineers and technicians to resolve the issue

R2

Financial problems

Medium

High

High

Checking and monitoring the financial condition and also the project budget. Creating a different fund for the outcomes may reduce this problem

R3

Computer server, network, and computing-related problems

High

High

Medium

Setting up the "RACK" system for the server computers could resolve this issue. Also, using backup and restore methods, in case of data damage, is a possible solution. Cloud computing (Cordeiro, 2017) also can resolve the server issues.

R4

Malfunctioning of power systems or ultimate failure

Medium

High

Medium

Using "UPS" (Uninterruptible Power Supply) for the computers and networking system, power generator for the overall power backup is the solution for the power failure issues

R5

Absenteeism or resigning of employees

Medium

Medium

Medium

Employing part-time workers for backup may be fruitful, also distributing the absentee's job between the other employees may resolve the problem

R6

Error or bug in the whole system network

Medium

High

High

Assigning experts and experienced engineers, technical experts should resolve the issue

R7

Outcomes and miscellaneous factors

Low

Medium

Medium

Strategically planning, monitoring, and understanding issue may work. Also, discussing the probable outcomes with higher authority is a useful method to solve this problem (Wibowo, 2018).

 

9.3. Managing the Risk

ID

Risk

Mitigation Procedure

R1

Hacking and cyber threats

Planning or strategy will not be able to solve this issue; the possible procedures are to discussing the problem details with the management authority of the project. Assigning an expert for these technical problems will help. The probable measures are, installing antivirus into the system will help to an extent. One of the other procedures is to encrypt the whole data (Nicola, Nicola, & Duta, 2018). It will convert the secured data to source code so the hackers or cyber threats will not be able to hack the system or steal the data and will be secured. Restricting new joiners to enter the network is also an excellent approach for it. Using a login id and password will protect the network from unauthorized access (Sivabalan & Radcliffe, 2018). Digital signatures could be used to secure the data when transferring between the single and multiple networks of the system.

R2

Financial problems

To mitigate this kind of problem, planning and strategy are required. One of the possible causes is a cost overrun and productivity delay that means an increase of budget to some considerable extent which was not in the plan. The possible causes are improper drawing and designing of the project, improper architect design, deficiency of raw materials to complete the project faster, high labor cost, lack of proper equipment, and machinery. Proper strategy and planning could resolve this kind of issue as identified on this Project Purpose Management assignment.

R3

Computer server, network, and computing-related problems

Mitigating strategy in this issue will reduce the risk. Stocking the essential hardware spares of the server computer like hard-disk, RAM, processors, and networking routers, switches will reduce the risk. This could be defined as hardware backup. Data and software backup also needed in this issue to minimize the risk. In case of any type of software crust, its backup will help to resolve the problem. Damaging of secured data is not impossible even after taking sufficient precautions and backup (Karabaševi, Stanujki, Brzakovi, Maksimovi, & Jevti, 2018). The Cloud computing network is another excellent solution to backing up data on cloud servers. Many branded companies provide this facility to secure data.

R4

Malfunctioning of power systems or ultimate failure

Uninterrupted power supply for the computers, servers, and networking equipment will help to reduce the damage due to sudden power failure. It causes damage to the hard-disk and processors severely. Also, the power generator is needed for a sufficient supply of power to the whole system.

R5

Absenteeism or resigning of employees

A proper mitigating plan and simple strategies will overcome this problem. There could be various factors behind this reason: illness, accidents, or other personal problems. Assigning a few part-time employees will reduce the risk of slow down the project work. Paying the employees within time will reduce their tendency to become absent. Also, the reward system should be considered for the employees. It will motivate them to work at an excellent pace to complete the job soon.

R6

Error or bug in the whole system network

Mitigating strategy in this problem will help to resolve this issue contacting, and assigning a proper expert is an excellent approach to solve this issue within less time. Bug is an error in case of software and it result to give unexpected error results. The main reason for bug is the mistakes done by the designer of the program or the main code of the file from which the program needs to be executed. Some errors occur due to improper compiling of the files. This is better to remove such programs containing bugs. Software experts are needed to be assigned to resolve this process.

R7

Outcomes and miscellaneous factors

Proper and regular monitoring can solve this type of issue and matches the criteria on the base of scopes.

 

10. Issue Management

Issues

Project Purpose Management assignmentDescription

Impact Level

Issues related to the suppliers

As this is a network-based project, thus it needs raw materials from the suppliers. The suppliers are responsible for delivering the proper raw materials to the resource engineer. Sometimes, the suppliers fail to supply the products on time (Liao, et al., 2018). It leads to create issues in the Project. Without proper raw materials,the Project is unable to proceed. It results in the delay of the Project. The issue can be avoided if there are multiple suppliers for providing raw materials. When one supplier gets unavailable, then the Organization can place the order to the other supplier (Sommerfeldt & Yang, 2017). As a result, the Process of the Project will work smoothly.

High

Issues on bargaining

The raw materials purchased from the suppliers must be bargained so that high cost does not spend on a particular material (Yawar & Seuring, 2017). The issues occur when there is a single supplier in the Organization, and the charge for particular Product got extreme. It must be mitigated by increasing the count of suppliers, and thus, the bargaining power can also be improved (Zhang & Borden, 2017). The test engineer must not depend upon the single source for the supply of the raw materials.

Medium

Issues on raw materials identified on this Project Purpose Management assignment

There are various types of raw materials that get destroyed due to weather change. It can create a massive loss for the Company. The Company must not spend a significant amount on such materials (Demirkesen & Ozorhon, 2017). There is another process of preventing the loss that is the materials must be maintained in a stable condition.

High

The issue of software tools

Several issues can occur in software tools. The software tools must be upgraded frequently to avoid the issues. The issues on the software tools lead to significant damage in the Organization (Sommerfeldt & Yang, 2017). The Organization must look for mitigation factors to solve the issues. The issues must be analyzed so that it does not occur in the future.

Medium

Issues on cost

The cost of the Project must be maintained while purchasing the items for the Project. The Project cost must not get exceeded to satisfy the clients. As a result, the Project might get fail. The cost issues can be mitigated by adopting sustainable methods on the Organization.

Medium

Issues on operations

Various issues occur while doing the operations of the Project. The operations must be planned expertly to meet the purpose of the Project. Project operations must not get affected due to the involvement of excessive persons on the management (Yawar & Seuring, 2017). The management process must be planned so that it can provide an excellent result to the Organization.

High

Issues on Project team

The issues in Project team can be small or large depending on the impact level. The issues on the Project team often lead to delay in the Project (Yawar & Seuring, 2017). The delay process must be mitigated by proper planning and quality plan of the management. Project manager, along with network manager, must monitor the Project Purpose Management assignment so that it can provide effective result.

Low

 

11. Procurement Management
11.1. Wagga Wagga

Items

Purchase Date

Delivery Date

Comments (the reason for delay)

Core i3/i5/i7 processor, 8GB RAM with HYPER-V technology/Esxi dedicated machine/core i5 processor, 2x4 GB RAM (2 dedicated machines)/Core i7 processor, 16GB RAM, nondedicated machine

18/03/2020

24/03/2020

Delivered within the proper delivery date

 

11.2. Griffith

Items

Purchase Date

Delivery Date

Comments (the reason for delay)

Core i3/i5/i7 processor, 8GB RAM with HYPER-V technology/Esxi dedicated machine/ Core i3 processor, 2x4 GB RAM (2 dedicated machines)

19/03/2020

25/03/2020

It was delivered on 27/03/2020 due to heavy rainfall. This is not possible for the supplier to deliver the computer and networking hardware because it may cause severe damage to the

Items

Purchase Date

Delivery Date

Comments (the reason for delay)

Core i3/i5/i7 processor, 8GB RAM with HYPER-V technology/Esxi dedicated machine/ Core i3 processor, 2x4 GB RAM (2 dedicated machines)

19/03/2020

25/03/2020

It was delivered on 27/03/2020 due to heavy rainfall. This is not possible for the supplier to deliver the computer and networking hardware because it may cause severe damage to the different parts of the machines.

Core i7 processor, 16 GB RAM, nondedicated machine

19/03/2020

26/03/2020

Delivered within the proper delivery date

Windows 10 Professional, Windows Server 2012 R2

20/03/2020

26/032020

Delivered within the proper delivery date

different parts of the machines.

Core i7 processor, 16 GB RAM, nondedicated machine

19/03/2020

26/03/2020

Delivered within the proper delivery date

Windows 10 Professional, Windows Server 2012 R2

20/03/2020

26/032020

Delivered within the proper delivery date

 

11.3. Albury

Items

Purchase Date

Delivery Date

Comments (the reason for delay)

Core i3/i5/i7 processor, 8GB RAM, HYPER-V/Esxi dedicated machine/core i3, 2x4 GB RAM, 2 dedicated machines/core i7, 16 GB RAM, non-dedicated machine

22/03/2020

28/03/2020

It was delivered on 29/03/2020 due to transport delays. It may happen due to heavy traffic on the way to the destination, any type of damages to the transport vehicle, and accident.

 

11.4. Orange

Items

Purchase Date

Delivery Date

Comments (the reason for delay)

Core i3/i5/i7 processor, 8GB RAM with HYPER-V technology/Esxi dedicated machine/ Core i3 processor, 2x4 GB RAM (2 dedicated machines)

24/03/2020

30/03/2020

Delivered of the Project Purpose Management assignment within the proper delivery date

 

12. Bibliography
Armstrong, M., & Taylor, S. (2020). Armstrong's handbook of human resource management practice. Kogan Page Publishers.
Bailey, C., Mankin, D., Kelliher, C., & Garavan, T. (2018). Strategic human resource management. Oxford University Press.
Baldwin, N., Chan, P., & De Morentin, E. (2019, 10 15). System verification of interactive screenshots and log files between client systems and server systems within a network computing environment. Google Patents.
Bratton, J., & Gold, J. (2017). Human resource management: theory and practice. Palgrave.
Cordeiro, J. (2017). Developing information systems with nomis: a model-driven systems development approach proposal. Seventh International Symposium on Business Modeling and Software Design.

DeCenzo, D., Robbins, S., & Verhulst, S. (2016). Fundamentals of human resource management. John Wiley & Sons.
Demirkesen, S., & Ozorhon, B. (2017). Impact of integration management on construction project management performance. International Journal of Project Management, 35(8), 1639-1654.
FRANCIS, N., & OLORI, W. (2017). TIME MANAGEMENT AND ORGANIZATIONAL EFFECTIVENESS: A STUDY OF MANUFACTURING COMPANIES IN PORT HARCOURT, NIGERIA. International Journal of Advanced Academic Research, 3(4).
Karabaševi, D., Stanujki, D., Brzakovi, M., Maksimovi, M., & Jevti, M. (2018). Importance of vulnerability scanners for improving security and protection of the web servers. Bizinfo (Blace), 9(1), 19-29.
Liao, Z., He, D., Chen, Z., Fan, X., Zhang, Y., & Liu, S. (2018). Exploring the characteristics of issue-related behaviors in github using visualization techniques. IEEE Access, 6, 24003-24015.
Nicola, M., Nicola, C.-I., & Duta, M. (2018). SCADA Systems Architecture Based on OPC and Web Servers and Integration of Applications for Industrial Process Control. International Journal of Control Science and Engineering, 8(1), 13-21.
Rezaei, E., Rostami, Y., Ghafouri, M., Fashkhorani, A., & Ahmadi, M. (2016). The infrastructure attitude to strategic planning of information technology in organizations. Marketing and Branding Research, 3, 97-108.
Sivabalan, S., & Radcliffe, P. (2018). Power Efficient Secure Web Servers. IJ Network Security, 20(2), 304-312. Sommerfeldt, E., & Yang, A. (2017). Relationship networks as strategic issues management: An issue-stage framework of social movement organization network strategies. Public Relations Review, 43(4), 829-839.
Sparrow, P., Brewster, C., & Chung, C. (2016). Globalizing human resource management. Routledge.
Wibowo, F. (2018). Implementation of strategic alignment framework for developing information technology of RFID in XYZ private university. Advanced Science Letters, 24(7), 5090-5093.
Yawar, S., & Seuring, S. (2017). Management of social issues in supply chains: a literature review exploring social issues, actions and performance outcomes. Journal of Business Ethics, 141(3), 621-643.
Zhang, X., & Borden, J. (2017). Linking issue management, corporate social responsibility and crisis communication: applying balance theory in crisis and issue management. Journal of Contingencies and Crisis Management, Project Purpose Management assignment, 25(4), 209-222.

13. Appendix of Project Purpose Management assignment
13.1 Network topology

Appendix-of-Project-Purpose-Management-assignment

13.2 WBS/Gantt chart for Project Purpose Management assignment

Appendix-of-Project-Purpose-Management-assignment

NEXT SAMPLE

Related Samples

Question Bank

Looking for Your Assignment?

Search Assignment
Plagiarism free Assignment

FREE PARAPHRASING TOOL

PARAPHRASING TOOL
FREE PLAGIARISM CHECKER

FREE PLAGIARISM CHECKER

PLAGIARISM CHECKER
FREE PLAGIARISM CHECKER

FREE ESSAY TYPER TOOL

ESSAY TYPER
FREE WORD COUNT AND PAGE CALCULATOR

FREE WORD COUNT AND PAGE CALCULATOR

WORD PAGE COUNTER



AU ADDRESS
9/1 Pacific Highway, North Sydney, NSW, 2060
US ADDRESS
1 Vista Montana, San Jose, CA, 95134
ESCALATION EMAIL
support@totalassignment
help.com